Pershore Infrastructure Update- July 2020

As promised, following Mark Mills presentation at the parish council meeting in February, here is an update on 3 areas directly affecting the parish from the Pershore Infrastructure plan. As you can see, due to Covid 19, deadlines have slipped but there are revised dates shown below.

Pinvin Crossroads

Works ongoing in full following Covid closure.

Expected completion by January 2021.

Further closures of Terrace Road, Pinvin to be announced shortly.

Night Closures of A44 for re-surfacing expected towards end of contract.

Link Road and Bridge

Reptile translocation exercise underway throughout the summer.

Main Contract expected to start in Autumn 2020.

Wyre Road

Design of road, footway and cycleway improvements ongoing.

Contract will be awarded in Spring 2021.